Midpoint Markers: Phase IV of Abaco Home Rehabilitation and Capacity Building Project

We are pleased to announce that our Abaco team has completed the rehabilitation of 11/22 homes of Phase IV: Abaco Home Rehabilitation and Capacity Building Project!

With 11 homes complete, we now have 6 under construction and 5 with materials on site.

We also are pleased to report the tremendous success of our Cash For Work team. Our team has dedicated over 25,470 hours of labor to Phase IV, earning more than $400,445.56 in wages. Additionally, the skills of countertop construction, cutting, and installation have been specifically developed over the past month of work; these trades will serve our Cash for Work team well in their pursuits when our work concludes on Abaco.